Case Studies
Real-world moves. Complex challenges. Zero-compromise outcomes. See how we've helped hospitals, research institutions, and surgery centers move their most critical equipment.
Success Stories
Medical Equipment Moving Success Stories
Each move is unique. Here's how we've tackled complex medical equipment relocations across the country.
3T MRI System Relocation — New Hospital Tower
Regional Medical Center, Houston TX
Challenge
A 750-bed regional hospital needed to move their Siemens Magnetom Vida 3T MRI to a new tower while maintaining clinical operations. The existing suite was on the 3rd floor with no direct freight access.
Solution
We engineered a custom rigging path using temporary structural supports and a specialized MRI sled system. Move was executed on a Saturday night from 10PM to 6AM.
Results
- Zero clinical downtime — scanner operational Monday morning
- Magnet quench successfully avoided
- Full move completed in 8 hours
- OEM accepted installation with no warranty issues
Full Laboratory Relocation — 18,000 Sq Ft Research Facility
BioGen Research Institute, Boston MA
Challenge
A biotech research institute needed to relocate an active BSL-2 laboratory — including HPLC systems, mass spectrometers, ultracentrifuges, and cryogenic storage — across town with strict chain-of-custody requirements.
Solution
We assembled a 12-person specialized team with BSL-2 decontamination certification. All equipment was documented, decontaminated, and moved in a single 72-hour window over a holiday weekend.
Results
- 18,000 sq ft lab relocated in 72 hours
- Full chain-of-custody maintained for all samples
- Zero equipment damage across 200+ items
- Research resumed within 5 days of move completion
da Vinci Xi Surgical Robot — Cross-Country Transport
Specialty Surgery Center, Los Angeles CA
Challenge
A surgery center purchased a pre-owned da Vinci Xi system from a hospital in New York and needed it shipped safely to Los Angeles with full OEM acceptance at the destination.
Solution
Our team coordinated with Intuitive Surgical for the de-installation protocol. The system was custom-crated in 9 individual components and shipped via climate-controlled FTL transport with shock loggers.
Results
- System arrived in perfect condition
- Shock logger showed zero events exceeding 0.5G
- Intuitive Surgical engineer completed acceptance testing
- OR operational within 4 days of delivery
CT Scanner Upgrade — Coordinated Old-For-New Swap
Imaging Center Group, Chicago IL
Challenge
A 5-site imaging center chain was replacing their GE Revolution CT scanners with Siemens Somatom Force systems at three locations simultaneously. They needed a coordinator to manage removal, shipping, and installation across all three sites on the same weekend.
Solution
We deployed three separate crews with a centralized operations coordinator. Old scanners were removed Friday night, new systems installed Saturday, and all three sites were scanning patients by Monday morning.
Results
- 3 simultaneous site replacements in 48 hours
- Zero revenue-day loss for any location
- Old scanners delivered to equipment broker on schedule
- All sites passed ACR phantom testing by Monday
Hospital Wing Renovation — 60-Piece Equipment Staging
University Health System, Philadelphia PA
Challenge
During a major ICU renovation, a university hospital needed 60+ pieces of patient monitoring equipment, ventilators, and infusion pumps stored offsite and returned in precise sequence as rooms came back online.
Solution
We provided secure climate-controlled warehousing for all equipment, tracked each piece with RFID inventory, and delivered equipment in phased sequences matching the renovation schedule.
Results
- 60+ items stored and staged over 6-month renovation
- 100% inventory accuracy throughout
- Phased delivery aligned with construction milestones
- Zero delays to renovation timeline
PET/CT Scanner Move — Working Hospital with No Closure
Cancer Treatment Center, Atlanta GA
Challenge
A busy cancer center needed to move their Siemens Biograph mCT PET/CT scanner 200 feet within the facility as part of a nuclear medicine department expansion — without closing the department.
Solution
We built a temporary shielded corridor for the transport path and executed the move in a single 12-hour overnight shift. Radiation safety compliance was maintained throughout with continuous RSO involvement.
Results
- Scanner moved without patient schedule disruption
- Continuous RSO-documented radiation safety compliance
- Moved 200 feet within facility in one overnight shift
- Clinical operations resumed the following morning
Start Your Project
Ready to Write Your Own Success Story?
Tell us about your medical equipment move and we'll create a plan that ensures the same zero-compromise outcome.